Scope of the Project Work: The Irmak-Karabük-Zonguldak Railway Line is 415 kilometres long. Currently it is a single line without signalization and electrification systems. The rehabilitation, signalization and telecommunication systems werebe constructed under the project. The project is divided into two phases. The First Phase comprises the Zonguldak-Karabük section (124 kilometres main line), while the Second Phase comprises the Karabük-Irmak section (291 kilometres main line).
PROJECT INFORMATION
Project Name: Rehabilitation and Signalization of Irmak-Karabük-Zonguldak Railway Line
Financial Contribution of the EU: 188 Million Euros
Total Project Amount: 228,3 Million Euros
Beneficiary Institution: General Directorate of Turkish State Railways