Scope of Work
Relevant equipment shall be supplied for the development of Smart Bike
System in Ankara under 4 LOTs.
LOT-1:
Scope of Work
•
•
•
•
Beneficiary Institution : EGO, Ankara Metropolitan Municipality
Contractor Company : BİMAŞ and RUBU Software
Date of the Contract : 06.07.2022
Starting Date of work : 15.08.2022
Completion Date of work : 13.03.2023
Project Budget :1.4 M €
LOT-2 :
Scope of Work
• Supply of 480 bike carrying apparatus
• 1290 m subway ramp
Beneficiary Institution : EGO ,
Contractor Company : Sevde Mimarlık
Date of the Contract : 06.07.2022
Starting Date of work :15.08.2022
Completion Date of work :13.12.2022
Project Budget : 0,25 M €
LOT-3 :
Scope of Work
• Supply of 2 bicycle transport vehicles
Beneficiary Institution: EGO ,
Contractor Company : Aday Grup
Date of the Contract : 06.07.2022
Starting Date of work: 15.08.2022
Completion Date of work: 13.12.2022
Project Budget : 89.700 €
LOT-4 :
Scope of Work
• Supply of 8 laptops
• Supply of 2 projectors
Beneficiary Institution : EGO ,
Contractor Company : Aday Grup
Date of the Contract : 06.07.2022
Starting Date of work :15.08.2022
Completion Date of work:14.10.2022
Project Budget :22.800 €