Progress Meeting and Site Visit for the Construction of Cerkezkoy-Kapikule Section of Halkali-Kapikule Railway Line Project Realised
Progress Meeting was held on 8 October 2024, followed by a site inspection visit on 9 October 2024 within the the scope of Project for the Construction of Cerkezkoy-Kapikule Section of Halkali-Kapikule Railway Line Project which is implemented under the Sectoral Operational Programme for Transport (USOP) as part of the Türkiye-EU financial cooperation managed by the Ministry of Transport and Infrastructure.
Representatives of the Directorate General of TCDD Modernisation Deparment, TCDD Site Control Organization, the NAO Office, the NIPAC, the Engineer and the Contractor were present during the project steering committee meeting, which was led by the Head of Department for EU Investments Tijen İğci (PhD).
A presentation covering the
general physical and financial progress of the project, as well as occupational
health and safety, environmental issues and community relations has been given
by the Contractor, during the meeting. Moreover, the points regarding the
remaining design works, on-going infrastructure and superstructure works, city
crossings, and issues that are carried out in coordination with other public
institutions and organizations have been discussed.