6th Progress Meeting on Construction of Cerkezkoy - Kapikule Section of Halkali - Kapikule Railway Line Project Realised
Sixth progress meeting on Construction of Çerkezköy - Kapıkule Section of Halkalı - Kapıkule Railway Line Project has been held with the participation of Contractor, Supervisor, European Union Delegation to Turkey, our Ministry and our Directorate General of TCDD representatives on 07.02.2020 in Ankara under the leadership of Deputy General Director of TCDD , Mr. İsmail ÇAĞLAR. 6.64% physical progress was achieved in the project. In addition, as of 31 January 2020, a total of 1316 contractor personnel are employed on the site and a total of 313 machines are used, including 51 excavators, 8 dozers, 19 loaders, 7 graders, 6 roller, 208 trucks, 6 JCB and 8 cranes.