4th Authority Liaison and Community Relations Meeting on Construction of Çerkezköy - Kapıkule Section of Halkalı - Kapıkule Railway Line Project has been held.
Authority
Liaison and Community Relations Team was established for the Construction of Çerkezköy
- Kapıkule Section of Halkalı - Kapıkule Railway Line Project. This team will
be in contact with the local people (landowners, neighbourhood representatives
etc.), record their complaints and requests, inform the relevant people /
institutions about the project, and ensure that the relevant people in the
local community has been informed before the start of construction in a certain
place on the site.
The team held
their first three meetings on June 2, June 17 and June 23 2020 this year. Finally,
on 7th of July2020 4th meeting has been held with the
participation of Contractor, Consultant, Ministry and TCDD representatives. In
the meeting, actions taken against received demands and complaints were
reviewed.